Project : Burgaz Wind Energy Farm (14,9 MW)
Employer : Demirer Enerji Üretim Sanayi Ve Ticaret A.Ş.
Job Description : Construction of 18 wind turbines, 5800 mt stabilized road and necessary art works, 18 stabilized covered platform structure, construction of control building,substation area and watchman buildings,under the name of Burgaz wind energy plant which shall be installed for Doğal Enerji A.Ş. at the location of Çanakkale province, Gelibolu district, Cevizli village, Burgaz – Munipbey Çiftliği.
Location : Gelibolu/ÇANAKKALE
Contract Date : 01.09.2006
Provisional Acceptance : 01.10.2007
Project Status : Finished

 

Specifications :
Bussiness Within The Scope Of Commitment

Business Items                                  :
 
·         Constuction of 5800 mt. stabilized road including all infrastructure and peripheral facillities
·         70.000 m3 excavation
·         15.000 m3 filling
·         5.000 m3 concrete
·         480 ton iron
·         15.000 ton stabilize
·         95.000 liters diesel
·         65 m3 Board

 